#20: Focusing on small usability enhancements

Overview
Start Date: 03/21/09 End Date: 04/10/09
8 items with a total relative size of 28 points
  
DONE tickets (13 points):
5
  
Sized tickets (15 points):
3
  
Partially Sized tickets (0 points):
0
  
Unsized tickets (0 points):
0
/ Total tickets (28 points):
8
agiletrac patch to core
agiletracplugin
iterations
release planning
roadmap UI customisation
Value
Id Summary Iterations Tested Documented Acceptance SIZE DONE
size done size done size done
agiletracplugin
#96 OperationalError?: ORDER BY terms must not be non-integer constants 20 0
  
0
  
0
  
0
release planning
#39 TracAdmin will be able to set the milestone priority from the 'admin' panel 19 20 23 25 3
  
0
  
0
  
3
agiletrac patch to core
#95 Roadmap errors after installing/upgrading to agile-trac 20 5
  
0
  
1
  
6
#94 Add 'owner' column to Iteration <x> work item table 20 0
  
0
  
0
  
0
roadmap UI customisation
#98 RoadmapUser? should be able to see an indication of what the estimated dates are based on 20 1
  
0
  
1
  
2
iterations
#99 IterationAdmin? should be able to associate wiki pages with an iteration for activities such as planning and evaluation 20 3
  
1
  
1
  
5
#93 EndUser? should have control over the display of the iteration work table, including what colums are shown and the default sort order 20 5
  
1
  
1
  
7
#97 AgileAdmin? should be able to 'reset' points per iteration in the event of drastic team changes 20 3
  
1
  
1
  
5